Projects To AR:
1.Create a Project using an appropriate Template with Tasks,Keymembers and
Customers who are having a valid Billing Contact.Change the Billing Setup as
COST/COST.
2.Create Agreements and Fundings for that Project.
3.Create Events accordingly. Give any type of Event for a Task. Number of lines of
an Invoice is dependent upon number of Events.
We can create any number of Events for a Task. All these Events will appear as
Lines in Invoice.
4.Define the Percent Complete i.e, Status of the Project and the date on which that
status is reached.
5.Create Approved Cost Budget and Approved Revenue Budget for the Project and
Baseline those Budgets.
6.Change the Project Status as Approved. Complete the Project Flexfield information.
7.Run the PRC: Generate Draft Revenue for a Single Project program to generate Draft
Revenue.Check this in Revenue Review.
8.Run the PRC: Generate Draft Invoices for a Single Project program
to generate Draft Invoice Check it in Invoice Review and Approve and Release that
Invoice.
9. Now, Run PRC: Interface Invoices to Receivables program to interface the Invoice
to Receivables.Now all the Invoices will be in RA_INTERFACE_LINES_ALL
10.Now, Run the Autoinvoice Master Program in Receivables. Batch Source is PROJECTS
INVOICES.
Now, the Invoices are successfully imported.
Or you can do in the below manner also for Foreign currency
Steps done in project creation
1.create project ie copy from existing projrcts go to projects and you can create here , for key memebrs and remaining things you can see the project wich you are copying and create same.
2.now go to Billing----> AGreement and here create funding and save the changes here .
3. now go to the BUDGET and here create budject and try to give amount and save and submit once you have submit then click baseline tab , if amount is not base lines then you have to give the conversion rate amount correctly to make it base line use below query for that
select CONVERSION_RATE*5000 from gl_daily_rates
where 1=1
and FROM_CURRENCY='EUR'
and TO_CURRENCY='USD'
and TRUNC (CONVERSION_DATE) = TO_DATE ('10-10-2008', 'DD-MM-YYYY')
4.Once you have done base line now we must creatre the expenditure items ... go to Expenditures------Pre Approved Batches ---Enter and here you can enter one new batch and create expenditure itemns..save the work and the click SUBMIT button and then Click Release button .
5.now go to Expenditures--->expenditures Inquiry--- Project here open your project and submit the request go to back end see if the concurrent program fails then run
PRC: Generate Draft Revenue for a Single Project for your single project.
6.once completeed then go to Billing--- Revenue Review and check your project and here Release.
7.Now go the expeditures ---- expenditure Inquiry---Project..... and here query for your project and open it and now RUn the Request once Request completed now
Run The request for single project PRC: Generate Draft Invoices for a Single Project
8.Go to Billing-----Inovice Review and check your invoice and expenditure how they appear and now
9. Now, Run PRC: Interface Invoices to Receivables program to
interface the Invoice to Receivables.
Now all the Invoices will be in RA_INTERFACE_LINES_ALL
10.Now, Run the Autoinvoice Master Program in Receivables. Batch Source
is PROJECTS INVOICES.
4 comments:
nice buddy
this is really cool
Shivdeep Singh
Hi
I read this post two times.
I like it so much, please try to keep posting.
Let me introduce other material that may be good for our community.
Source: Project accountant interview questions
Best regards
Henry
Nice artical to learning PA to AR process but one thing can you please share Screen Shots also it is very helpful for every one
Thanks,
SURESH SIKHA
This is my first opportunity to visit this website I found some interesting things and I will apply to the development of my blog.
accounting howmework help
Post a Comment